PURPOSE
The purpose of this assignment is to enable you to:
• Articulate a thorough understanding of the basic principles and practices of measurement and estimating.
• Demonstrate the use of the Standard Method of Measurement as used in the Australian construction industry.
• Measure quantities and estimate unit rates to prepare tenders for common types of low and medium-rise construction.
• Apply information technology in measurement and estimating.
SRQ774 Construction Measurement And Estimating Assignment 

SRQ774 Construction Measurement And Estimating Assignment 

ASSIGNMENT TASK
For this task it is important to appreciate that your role has changed. In Assignment 1 you were operating in the manner of a cost consultant or quantity surveyor representing the client. Your task simply stated was to prepare a tender document (BQ), which would be sent to several contractors. These contractors would then use the BQ to prepare their bids in competition with other contractors to win the project. Your task now is to operate in the same manner as a team of estimators working for one of the tendering contractors.

SRQ774 Construction Measurement And Estimating Assignment 

For Assignment 3 you are required to calculate unit rates for the items within the following work sections which appear in your BQ for the project Deakin University Burwood Highway Frontage:

A. Groundworks
• Topsoil (vegetable soil) excavation
• Bulk excavation (basement excavation)
• Pit excavations for pad footings (PF1 – PF9) and raft footings (RF1 and RF2)
• Trench excavation for strip footings (SF1 and SF2)

SRQ774 Construction Measurement And Estimating Assignment 

B. Concrete works
• Pad footings (PF1-PF9) and raft footings (RF1 and RF2)
• Strip footings (SF1 and SF2)
• Columns on Basement 3
• Basement 3 Slab (excluding ramps and stairs)
• Blinding concrete under pad footings (PF1 – PF9) and raft footings (RF1 and RF2)

SRQ774 Construction Measurement And Estimating Assignment 

C. Formworks
• Pad footings (PF1-PF9) and raft footings (RF1 and RF2)
• Strip footings (SF1 and SF2)
• Columns on Basement 3

D. Reinforcement
• Reinforcement for pad footings (PF1 – PF6)
• Reinforcement for Raft footings (RF1 and RF2)

SRQ774 Construction Measurement And Estimating Assignment 

Please note that you have already prepared an unpriced BQ for some of the items Ground works concrete works and Formworks) in your Assignment 1. You are allowed to integrate your Assignment 1 information when completing this task. However, you should measure reinforcement since the quantities of reinforcement were not determined in Assignment 1. You are required to measure the works and prepare BQ in accordance with the requirements of the Standard Method of Measurement that are applicable in Australia (i.e based on ANZSMM or ASMM-6).

Please include the following in the Assignment 3 report:

SRQ774 Construction Measurement And Estimating Assignment 

SRQ774 Construction Measurement And Estimating Assignment 

I. Summary of total estimated cost;
II. Priced BQ
a. Enter unit rates for each BQ item and extend the rates to determine the cost
for each of the work sections and a total cost for the works.
III. Build-up rates for each item.
a. You are required to compute the build-up rates based on material, plant and labour costs. Note that the aim of this task is to calculate the unit rates and not look up the rates in Rawlinson’s or some other reference book you may however use Rawlinsons to cross-check your build up rates.
b. All unit rate build-up calculations produced must be attached to your report. The calculations can be printed using the copy or print screen function and is acceptable for this assignment.
IV. Individual reflection from each group member and
V. All reference materials used in rate build-ups.

SRQ774 Construction Measurement And Estimating Assignment 

The assignment will be carried out on a group basis. Each group should consist of a maximum of 4 students. All group members are required to be involved and contribute to the assignment. Group members should communicate with the unit chair if there are any group conflicts that cannot be resolved prior to submission.

FORMAT OF ASSIGNMENT
Assignment 3 report must be submitted as a single A4 PDF document which will include your priced BQ, calculations rate build-ups and individual reflection.

SRQ774 Construction Measurement And Estimating Assignment 

The task must be completed using a suitable software package CostX or MS Excel. Prepare all your work in a neat, tidy and professional manner.

ORDER This SRQ774 Construction Measurement And Estimating Assignment  NOW And Get Instant Discount

Order Your Assignment
Contact us on WhatsApp Assignment help payment - PayPal



Assignment Help In Australia - Essay Help
69 Kent St Millers Point NSW 2000 Australia
Phone : +61-3-6387-7039

Disclaimer: The papers provided by Assignmenthelpinaustralia.com serve as model papers for research candidates and are not to be submitted 'as is'. These papers are intended to be used for reference purposes only.
Assignmenthelpinaustralia.com only offers consultation and research support and assistance in research design, editing, and statistics.*